Installation Guideline: BaseGrid Base Stabilization Geogrids
Preparation
- The engineer should verify the subgrade is ready for BaseGrid base stabilization geogrid placement and that elevations are as indicated on the contract drawings.
- The surface should be fairly smooth and free of stumps, sharp objects and debris that may damage the base stabilization geogrid. Tree stumps should be cut at ground level.
Installation
- Unroll BaseGrid geogrid on the subgrade and apply tension to eliminate wrinkles.
- Geogrid panel overlap requirements, either side-by-side or end-to-end, should depend on the strength of the subgrade.
- For very soft subgrade (with CBR = 1-2), 2 feet overlap is recommended.
- For firm subgrade (CBR > 2), 1 foot overlap is recommended.
- Adjacent BaseGrid geogrid rolls should be overlapped in the direction of anticipated fill spreading.
Base Material Placement Over the Geogrid
FIRM SUBGRADE
- When applying the fill material over firm ground (CBR > 2), rubber tire trucks (end and belly dumps) can drive directly on the geogrid at very slow speeds (less than 5 mph) and dump the fill material as they go.
- Operators must not turn or make any sudden stops when driving across the BaseGrid geogrid.
- Tracked vehicles cannot be driven on the geogrid.
- A minimum of four inches of fill material should be placed between the BaseGrid base stabilization geogrid and tracks.
SOFT SUBGRADE
- When applying fill material over soft ground (CBR between 1-2) and very soft ground (CBR <1), no equipment can drive directly on the BaseGrid geogrid.
- A minimum of four inches of fill is required between the base stabilization geogrid and the operating vehicles.
- Tight turns, sudden stops or spinning tracks are prohibited.
- Low ground pressure tractors and low tire pressures (less than 4 psi) are recommended for hauling and spreading fill over soft subgrade.
- Back dump specified fill materials onto the base stabilization geogrid where the subgrade is most stable and then spread the fill over the geogrid out toward the weaker subgrade.
- Haul trucks should not drive on the fill material until total compacted fill thickness has been achieved.
- Any ruts developed during spreading or compacting must be filled with additional fill material to reach the design thickness.
- Base course material should be placed and compacted in the lift thickness specified in the design requirements.
Repair
- BaseGrid geogrid sections damaged during installation must be repaired by patching. Place a geogrid patch to cover damaged geogrid area and extend 3 feet beyond in all directions.
Protection
- The BaseGrid base stabilization geogrid should be protected from long-term exposure to direct sunlight during transport and storage.
- After placement, the geogrid should not be left uncovered for more than 3 weeks.
Spec Interpretation